Water And Electricity Going In

The car park base and kerbs are almost complete, as is the new entrance splay.

The water main, electricity ducts and wastewater pipes are being laid under what will be a pedestrian footpath alongside the access road.

The first top surface of tarmac will be laid in the car park next week.