Work on pitches continuing apace

The continuing good weather has enabled rapid progress to be made on our two pitches.

As shown in the first two pictures, the smaller training/community pitch is looking good, having had all the perimeter fencing erected and the floodlight pylons installed.   The playing surface carpet will be laid on this pitch in about four weeks.

The third picture shows that the main pitch is now level, and we anticipate that the tarmac layer will go down in the next couple of weeks.